○ Date and Time:
1st blackout: Friday, October 15th, 2010. 05:00~24:00.
2nd blackout: Saturday, October 16th, 2010. 00:00~18:00.
3rd blackout: Sunday, October 17th, 2010. 07:00~18:00.
○ Specific Schedule
|
Time |
Affected Buildings |
1st Power Plant |
Friday, October 15th, 05:00 ~ 08:00 | 1, 2, 13, 20, 22, 23, 47, 49, 59, 60, 62, 64, 71-2, 82, 83, 109, 113, 130, 131, 133, 140, 140-1 |
Friday, October 15th, 05:00 ~ 11:00 | 21, 21-1, 43 | |
Saturday, October 16th, 05:00 ~ 08:00 | 50, 51, 52, 52-1, 52-2, 53, 54, 55, 57, 58, 63, 68, 68-2, 70, 71, 71-1, 73, 74, 103, 117, 121, 137, 137-1, 137-2, 144, 207, 919, 920, 921, 922, 923, 924, 925, 926, 941, Guksoo-bong, B-Gate, C-Gate | |
Saturday, October 16th, 00:00 ~ 08:00 | 15, 17, 84, 16-1, 72, Asian Studies construction site | |
Saturday, October 16th, 09:00 ~ 12:00 | 24, 25-1 | |
Saturday, October 16th, 13:00 ~ 16:00 | 29, 139, 141 | |
Saturday, October 16th, 16:00 ~ 18:00 | 150 | |
Saturday, October 16th, 08:00 ~ 11:00 | 16, 16-A, 149 | |
Saturday, October 16th, 08:00 ~ 16:00 | 67, A-Gate | |
2nd Power Plant |
Sunday, October 17th, 07:00 ~ 10:00 | 45, 48, 48-1, 104, 104-1, 104-2, 104-3, 105, 105-1, 107-1, 107-2, 107-3, 132 |
Friday, October 15th, 22:00 ~ Saturday, October 16th, 06:00 | 200, 201, 203, 75, 75-1 | |
Saturday, October 16th, 04:00 ~ 06:00 | 500, 506 | |
Sunday, October 17th, 08:00 ~ 09:00 | 301, 310, 311, Ja-un temple | |
Sunday, October 17th, 11:00 ~ 13:00 | 30, 30-1, 30-2, 31-1, 33 | |
Sunday, October 17th, 13:00 ~ 16:00 | 31, 32 | |
Sunday, October 17th, 16:00 ~ 18:00 | 34, 36 | |
Sunday, October 17th, 07:00 ~ 17:00 | 37, Haedong construction site | |
3rd Power Plant |
Friday, October 15th, 22:00 ~ Saturday, October 16th, 03:00 | 57-1, 220, 221, 222 |
○ Power Outage Details: electric capacity extension operation by EHP installment on 45 buildings
○ Request for Cooperation:
A. To minimize any inconveniences please announce the power outage prior to the operation date
B. To prevent any damages, please prepare for the operation in advance.
C. To prevent damages of electrical devices, please separate the plug from the power supply before
the operation.
D. After power is supplied, resume electricity use only after taking safety procedures.
E. Extra attention is required for crime prevention and security as the security apparatus (CCTV and
other crime prevention devices) may be interrupted.