Power Outage Notice (October 15th ~ 17th)

Please be notified there will be a power outage for the load-adjustment of high-voltage electric substations, capacity expansion for extra high-voltage electricities in accordance with the energy save operation on Gwanak Campus. We apologize in advance for the inconvenience.

○ Date and Time: 
   1st blackout: Friday, October 15th, 2010. 05:00~24:00. 
   2nd blackout: Saturday, October 16th, 2010. 00:00~18:00. 
   3rd blackout: Sunday, October 17th, 2010. 07:00~18:00.

○ Specific Schedule

 

Time

Affected Buildings

1st Power Plant

Friday, October 15th, 05:00 ~ 08:00

1, 2, 13, 20, 22, 23, 47, 49, 59, 60, 62,  64, 71-2, 82, 83, 109, 113, 130, 131, 133, 140, 140-1

Friday, October 15th, 05:00 ~ 11:00

21, 21-1, 43

Saturday, October 16th, 05:00 ~ 08:00

50, 51, 52, 52-1, 52-2, 53, 54, 55, 57, 58, 63, 68, 68-2, 70, 71, 71-1, 73,  74, 103, 117, 121, 137, 137-1, 137-2, 144, 207, 919, 920, 921, 922, 923, 924, 925, 926, 941, Guksoo-bong, B-Gate, C-Gate

Saturday, October 16th, 00:00 ~ 08:00

15, 17, 84, 16-1, 72, Asian Studies construction site

Saturday, October 16th, 09:00 ~ 12:00

24, 25-1

Saturday, October 16th, 13:00 ~ 16:00

29, 139, 141

Saturday, October 16th, 16:00 ~ 18:00

150

Saturday, October 16th, 08:00 ~ 11:00

16, 16-A, 149

Saturday, October 16th, 08:00 ~ 16:00

67, A-Gate

2nd Power Plant

Sunday, October 17th, 07:00 ~ 10:00

45, 48, 48-1, 104, 104-1, 104-2, 104-3, 105, 105-1, 107-1, 107-2, 107-3, 132

Friday, October 15th, 22:00 ~ Saturday, October 16th, 06:00

200, 201, 203, 75, 75-1

Saturday, October 16th, 04:00 ~ 06:00

500, 506

Sunday, October 17th, 08:00 ~ 09:00

301, 310, 311, Ja-un temple

Sunday, October 17th, 11:00 ~ 13:00

30, 30-1, 30-2, 31-1, 33

Sunday, October 17th, 13:00 ~ 16:00

31, 32

Sunday, October 17th, 16:00 ~ 18:00

34, 36

Sunday, October 17th, 07:00 ~ 17:00

37, Haedong construction site
3rd Power Plant

Friday, October 15th, 22:00 ~ Saturday, October 16th, 03:00

57-1, 220, 221, 222

○ Power Outage Details: electric capacity extension operation by EHP installment on 45 buildings

○ Request for Cooperation: 
   A. To minimize any inconveniences please announce the power outage prior to the operation date
   B. To prevent any damages, please prepare for the operation in advance.
   C. To prevent damages of electrical devices, please separate the plug from the power supply before 
       the operation.
   D. After power is supplied, resume electricity use only after taking safety procedures.
   E. Extra attention is required for crime prevention and security as the security apparatus (CCTV and
       other crime prevention devices) may be interrupted.

Seoul National University